2PIM-CI – GP
This patented completion system used for isolation upper reservoir of a casing providing optimal operation of tubing in wells with high gas-oil ratio. It includes two packers with cable inlet (CI) and gas pipe (GP) with an ESP unit.
Applications:
- For cost reduction in multi-reservoir fields;
- Shutting in upper reservoir with minimal production costs;
- Interval isolation with a leaking production casing in production wells with a high gas-oil ratio.
BENEFITS
- Ease of installation and high performance of the completion system for isolation of complicated reservoir and quick operation of the well without conducting multistage run and set operations;
- Stable operation of the ESP without cuttings-off the flow in a well with a high gas-oil ratio and with a leaking production casing above the productive reservoir;
- The completion is run and set in the well in one stage.
Item code | Casing string, mm./in. | Min. drift diameter, mm/in | Max.working pressure, Mpa/psi | Maximum T, ℃/F | Packer thread diameter, mm | Downhole environment | |
Nominal diameter | Wall thickness | ||||||
2PIM-CI – GP -120 | 146/5.74 | 6,5-11/
0.23-0.39 |
27/1.06 | 35/5076 | 120/248; 150/302 ⃰ | Upper 60
Lower 73 |
Oil
Associated gas Gas Condensate Natural gas Formation water |
2PIM-CI – GP -140 | 168/6.61 | 7-11/
0.3-0.43 |
27/1.06 | 35/5076 | 120/248; 150/302 ⃰ | Upper 60
Lower 73 |
|
178/7 | 13-15/
0.51-0.59 |
||||||
2PIM-CI – GP -145 | 168/6.61 | 7,3-8/
0.27-0.31 |
27/1.06 | 35/5076 | 120/248; 150/302 ⃰ | Upper 60
Lower 73 |
|
178/7 | 11,5-12,7/
0.43-0.47 |
* by personal request