2PIM-CI – GP

This patented completion system used for isolation upper reservoir of a casing providing optimal operation of tubing in wells with high gas-oil ratio. It includes two packers with cable inlet (CI) and gas pipe (GP) with an ESP unit.

Applications:

  • For cost reduction in multi-reservoir fields;
  • Shutting in upper reservoir with minimal production costs;
  • Interval isolation with a leaking production casing in production wells with a high gas-oil ratio. 

BENEFITS

  • Ease of installation and high performance of the completion system for isolation of complicated reservoir and quick operation of the well without conducting multistage run and set operations;
  • Stable operation of the ESP without cuttings-off the flow in a well with a high gas-oil ratio and with a leaking production casing above the productive reservoir;
  • The completion is run and set in the well in one stage.
Item code Casing string, mm./in. Min. drift diameter, mm/in Max.working pressure, Mpa/psi Maximum T, ℃/F Packer thread diameter, mm  Downhole environment
Nominal diameter Wall thickness
2PIM-CI – GP -120 146/5.74 6,5-11/

0.23-0.39

27/1.06 35/5076 120/248; 150/302 ⃰ Upper 60

Lower 73

Oil

Associated gas

Gas Condensate

Natural gas

Formation water

2PIM-CI – GP -140 168/6.61 7-11/

0.3-0.43

27/1.06 35/5076 120/248; 150/302 ⃰ Upper 60

Lower 73

178/7 13-15/

0.51-0.59

2PIM-CI – GP -145 168/6.61 7,3-8/

0.27-0.31

27/1.06 35/5076 120/248; 150/302 ⃰ Upper 60

Lower 73

178/7 11,5-12,7/

0.43-0.47

* by personal request